• UHV-430 HV و LV Switchgear اختبار سرير الاختبار

    UHV-430 switchgear test equipment used for high and low voltage switchgear manufacturers to produce the high and low voltage switchgear before the factory power test. The high and low voltage switchgear power test bench can provide a variety of AC and DC power supplies to facilitate the detection of switchgear and improve work efficiency.

    تفاصيل المنتج لمنصة اختبار لوحة المفاتيح الكهربائية UHV-430 HV وLV


    Product Introduction

    The UHV-430 HV/LV Switchgear Energized Test-Bed is designed for manufacturers to perform various energized tests on high-voltage and low-voltage switchgear prior to delivery. It provides a variety of AC and DC power supplies, facilitating convenient switchgear measurement and improving work efficiency.


    Product Characteristics

    1. Versatile Power Supply: Provides a variety of AC and DC power outputs to meet different testing requirements.

    2. Enhanced Efficiency: Enables convenient measurement of switchgear, significantly improving work efficiency.


    المعايير الفنية

    Input powerthree-phase four-wire AC380V
    الناتج الجهد والتيارThree-phase AC100V output (fixed value)1 group
    Three-phase AC 0~10A output (100V, adjustable value)1 group
    AC voltage output AC 0~400V, when 220V, current less than 10A1 group
    DC operating voltage output DC 0~260V1 group
    Single-phase AC220V output (fixed value, socket)2 groups
    Three-phase AC380V output (fixed value, terminal)1 group
    Fixed DC voltage 24V, 36V, 110V, 220V output1 group
    البعد550×750×800 ملم3
    وزن45 كجم


    Instructions 

    1. Connect three-phase four-wire AC380V. 

    2. Connect output DC300V to the load. 

    3. Counterclockwise rotate the output adjustment knob to zero. 

    4. Check whether the wiring is correct.

    5. Close power switch. 

    6. Slowly adjust output adjustment knob, boost voltage to the desired value. 

    7. Completed test, counterclockwise rotate the output adjustment knob to zero, and then disconnect the power switch, wait for finishing discharge, you can remove the test lead.








    قد يعجبك ايضا

    • لديك أي أسئلة!

      لا تتردد في الاتصال بنا في أي وقت
      اتصل بنا
    • زورنا

      المبنى رقم 6، مجمع أوبتكس فالي الصناعي البصري الميكانيكي، 84 طريق جاوكسين 5،
      منطقة تطوير التكنولوجيا الجديدة في البحيرة الشرقية، مدينة ووهان، مقاطعة هوبي، الصين

    • ارسل لنا عبر البريد الإلكتروني

      تشياو@hvtest.cc

    • اتصل بنا

      +86-15871365102